A hard rock mine is driving a new decline at about 15 feet a day. A month later the face is 450 feet past the last leaky feeder amplifier, and the jumbo operator has to walk back to a refuge station to call the surface. Development moved fast. The radio did not. This post follows that decline through a year of work to show how mine communications can be planned to keep up with the face.

Ordering From the Mine Plan

The mine plan already says where each heading will go over the next year and how fast. That plan is also the radio plan. Every new heading needs leaky feeder cable, and long runs need line amplifiers spaced along them. Those parts can take several weeks to arrive. If the order goes in when the face is already out of range, the crew works without radio for weeks. If it goes in from the development schedule, the parts are on site before the face needs them. For our decline, that means ordering cable and an amplifier about two months ahead of where the face will be.

Checking How Far the System Can Stretch

Before adding cable, someone needs to know how much headroom the system has left. Each amplifier adds a little noise along with its gain, so every leaky feeder system has a limit on how many amplifiers can be chained in a row. Near that limit, more cable only makes the far end noisier. At that point a new branch off the main line, or a trunk line with more capacity, extends coverage more cleanly. Power belongs in the same check. Line amplifiers draw their power through the cable from supplies placed along the system. If mine power fails during a fire or a roof fall, the radios still have to work, so those supplies need battery backup. The MINER Act of 2006 requires underground coal mines to keep two-way contact with the surface, even after an accident.

Keeping the Cable Alive Near the Face

The newest cable lives in the roughest spot in the mine. Flyrock from each blasted round hits it, and loaders and trucks snag it on the way through. Hanging it high on the rib with breakaway hangers, on the side away from haul traffic, cuts most of that damage. A spare coil and a spare amplifier kept close by let a crew repair a break the same shift. Every cable route, splice and amplifier location then goes on the mine map. When a section goes quiet, the map points the technician to the likely failure, and the next extension starts from good records.

Mines planning extensions can review leaky feeder systems and cable from Becker Wholesale Mine Supply, which supplies VHF and UHF options for growing underground operations.